 |
Projects
CURRENT PROJECTS:
- MDOT M-66 Reconstruction – Ionia
- Parkview Avenue Sidewalk – Kalamazoo
- MDOT Kalamazoo Street Reconstruction – Lansing
- Marshall High School Parking Lot Reconstruction – Marshall
- MDOT I-94/11 Mile Road Ramp Realignment – Calhoun County
- MDOT Haslett Road/M-52 Reconstruction – Ingham County
- MDOT Sprinkle Road Reconstruction – Kalamazoo County
- Four Winds Casino Hotel and Convention Center Addition – New Buffalo
- Four Winds Casino (Satellite) – Hartford
- Firekeepers Casino Hotel and Convention Center Addition – Battle Creek
- Kellogg Community College Lane Thomas Building – Battle Creek
- MDOT Berry Road Bridge – Jackson County
- MDOT I-94 / Sargent Road Interchange Reconfiguration – Jackson County
- Lift Station Replacement – Battle Creek
- MDOT Portage, Oakland and Westnedge – Portage
- INDOT Linden Road Bridge – Lakeville, Indiana
- Fuller Road Station Interceptor Sewer Relocation – Ann Arbor
- Navy Operational Support Center – Fort Custer Training Center, Battle Creek
- Fort Custer Training Center 2011 Paving – Battle Creek
- Frankfort Airport Parallel Taxiway – Frankfort, Indiana
- VA Medical Center – Battle Creek
FEATURED PROJECTS:
- FOUR WINDS CASINO
Location: New Buffalo, Michigan
Owner: Pokagon Band of Potawatomi Indians
Contract Amount: N/A
Completion: 2006
Project Description: Earthwork and utility infrastructure for the new Four Winds Casino Resort. This project involved grading and improvements on approximately 200 acres. The majority of the sitework was completed in a six month time frame.
Major Items of Work:
- Earthwork
- Storm Sewer
- Sanitary Sewer
- Water Main
- Sand Subbase
- Geogrid
- Aggregate Base
|
250,000 cubic yards
13,000 feet
8,000 feet
10,000 feet
50,000 cubic yards
74,700 square yards
144,300 square yards
|
- CSO CONTROL – SEWER SEPARATION AREA 013 NORTHEAST
Location: Lansing, Michigan
Owner: City of Lansing
Contract Amount: $7,652,046.00
Completion: 2008
Project Description: Separation of existing combined sewer through construction of new independent sanitary sewer and storm sewer systems. The project included replacement of the existing water main system and complete reconstruction of all affected streets.
Major Items of Work:
- Pavement Removal
- 12-54” Storm Sewer
- Sanitary Sewer
- Water Main
- CIPP Sewer Lining
- Subbase
- Aggregate Base
- Concrete Curb/Gutter
- Concrete Sidewalk
- Asphalt Paving
|
35,000 square yards
3,800 feet
19,980 feet
10,000 feet
19,300 feet
11,100 cubic yards
56,700 square yards
10,000 feet
12,500 square feet
14,000 tons
|
- I-94 BUSINESS LOOP (Main Street)
Location: Benton Harbor, Michigan
Owner: MDOT
Contract Amount: $12,005,234.00
Completion: 2010
Project Description: Reconstruction of 1.78 miles I-94 BL (Main Street) through downtown Benton Harbor. The project involved complete reconstruction of the roadway including new sanitary sewer, water main and storm sewer. 100% of the existing concrete road was recycled and reincorporated back into the project as aggregate base. The completed project includes two roundabouts, bicycle lanes, on-street parking, streetscape elements and traffic signal modernization.
Major Items of Work:
- Pavement Removal
- Storm Sewer
- Sanitary Sewer
- Water Main
- CIPP Sewer Lining
- Subbase
- Aggregate Base
- Concrete Curb/Gutter
- Concrete Sidewalk
- Asphalt Paving
|
156,000 square yards
10,900 feet
16,052 feet
13,711 feet
7,030 feet
43,401 cubic yards
75,000 square yards
29,400 feet
168,600 square feet
30,000 tons
|
 |
National Partnership for Highway Quality
Award Winner |
- W.K. KELLOGG AIRPORT – RUNWAY 5R/23L
Location: Battle Creek, Michigan
Owner: City of Battle Creek
Contract Amount: $6,625,015.00
Completion: 2011
Project Description: Construction of a new parallel runway at W.K. Kellogg Airport. The project involved approximately 285,000 cubic yards of total earthwork. 30,000 cubic yards of muck excavation and over 50,000 cubic yards of fill material imported from off site. New airfield lighting and a new electrical vault building were also constructed as part of the project.
Major Items of Work:
- Muck Excavation
- Imported Fill
- Subbase
- Aggregate Base
- Restoration
- 12-42” Storm Sewer
- Underdrain
- Asphalt Paving
|
32,000 cubic yards
55,000 cubic yards
63,600 cubic yards
82,500 square yards
74 acres
8,250 feet
21,000 feet
15,840 tons
|
- KALAMAZOO RIVER INVERTED SIPHON REPLACEMENT
Location: Battle Creek, Michigan
Owner: City of Battle Creek
Contract Amount: $1,533,617.00
Completion: In Progress, Complete Spring 2012
Project Description: Construction of a new twin pipe inverted sanitary sewer siphon with new cast in place concrete diversion chamber and outlet structure. The river crossing work was accomplished inside a cofferdam first installed on the north side of the river and then later on the south side.
Major Items of Work:
- 24” and 30” DI Pipe
- Concrete Encasement
- 42” CIPP Re-line of Existing
|
840 feet
380 feet 420 feet
|
- DOWNTOWN TRANSFORMATION STREETSCAPE
Location: Battle Creek, Michigan
Owner: City of Battle Creek
Contract Amount: $7,795,243.00
Completion: In Progress, Complete Fall 2012
Project Description: Complete reconstruction of Michigan Avenue through the downtown Battle Creek business district. This project is being constructed in 3 phases to minimize the impact of construction on the downtown business district. The scope of the project included replacement of the aging water main and storm sewer infrastructure prior to reconstruction of the roadway. The project also includes numerous streetscape elements such as a fire pit, water fountain and a 40 foot long glass and metal sculpture.
Major Items of Work:
- Storm Sewer
- Water Main
- Concrete Curb/Gutter
- Concrete Paving
- Concrete Sidewalk
- Decorative Concrete
- Brick Paving
- Asphalt Paving
- Precast Concrete Benches
- Street Lighting System
|
2,500 feet
3,700 feet
7,890 feet
5,585 square feet
50,000 square feet
5,895 square feet
96,000 square feet
3,725 tons
70 each
|
|






|
|