Contractors Since 1947
Hoffman Services - road construcion - underground - sitework - recycling Michigan Indiana road highway airport contractors bids Michigan Indiana Construction Projects Contractors Examples Sitework & Road Construction History Hoffman Bros contact - sitework - airport - underground - aggregate recycling

Projects

CURRENT PROJECTS:

  • MDOT M-66 Reconstruction –  Ionia
  • Parkview Avenue Sidewalk – Kalamazoo
  • MDOT Kalamazoo Street Reconstruction – Lansing
  • Marshall High School Parking Lot Reconstruction – Marshall
  • MDOT I-94/11 Mile Road Ramp Realignment – Calhoun County
  • MDOT Haslett Road/M-52 Reconstruction – Ingham County
  • MDOT Sprinkle Road Reconstruction – Kalamazoo County
  • Four Winds Casino Hotel and Convention Center Addition – New Buffalo
  • Four Winds Casino (Satellite) – Hartford
  • Firekeepers Casino Hotel and Convention Center Addition – Battle Creek
  • Kellogg Community College Lane Thomas Building – Battle Creek
  • MDOT Berry Road Bridge – Jackson County
  • MDOT I-94 / Sargent Road Interchange Reconfiguration – Jackson County
  • Lift Station Replacement – Battle Creek
  • MDOT Portage, Oakland and Westnedge – Portage
  • INDOT Linden Road Bridge – Lakeville, Indiana
  • Fuller Road Station Interceptor Sewer Relocation – Ann Arbor
  • Navy Operational Support Center – Fort Custer Training Center, Battle Creek
  • Fort Custer Training Center 2011 Paving – Battle Creek
  • Frankfort Airport Parallel Taxiway – Frankfort, Indiana
  • VA Medical Center – Battle Creek

FEATURED PROJECTS:

  • FOUR WINDS CASINO

    Location:  New Buffalo, Michigan
    Owner:  Pokagon Band of Potawatomi Indians
    Contract Amount: N/A
    Completion: 2006

    Project Description: Earthwork and utility infrastructure for the new Four Winds Casino Resort. This project involved grading and improvements on approximately 200 acres. The majority of the sitework was completed in a six month time frame.

    Major Items of Work:

    • Earthwork    
    • Storm Sewer   
    • Sanitary Sewer  
    • Water Main  
    • Sand Subbase
    • Geogrid         
    • Aggregate Base 
    250,000 cubic yards
    13,000 feet
    8,000 feet
    10,000 feet
    50,000 cubic yards
    74,700 square yards
    144,300 square yards

  • CSO CONTROL – SEWER SEPARATION AREA 013 NORTHEAST

    Location:  Lansing, Michigan
    Owner:  City of Lansing
    Contract Amount:  $7,652,046.00
    Completion: 2008

    Project Description: Separation of existing combined sewer through construction of new independent sanitary sewer and storm sewer systems. The project included replacement of the existing water main system and complete reconstruction of all affected streets.

    Major Items of Work:

    • Pavement Removal 
    • 12-54” Storm Sewer
    • Sanitary Sewer  
    • Water Main  
    • CIPP Sewer Lining 
    • Subbase         
    • Aggregate Base  
    • Concrete Curb/Gutter
    • Concrete Sidewalk  
    • Asphalt Paving    
    35,000 square yards
    3,800 feet
    19,980 feet
    10,000 feet
    19,300 feet
    11,100 cubic yards
    56,700 square yards
    10,000 feet
    12,500 square feet
    14,000 tons

  • I-94 BUSINESS LOOP (Main Street)

    Location:  Benton Harbor, Michigan
    Owner:  MDOT
    Contract Amount:  $12,005,234.00
    Completion: 2010

    Project Description:  Reconstruction of 1.78 miles I-94 BL (Main Street) through downtown Benton Harbor. The project involved complete reconstruction of the roadway including new sanitary sewer, water main and storm sewer. 100% of the existing concrete road was recycled and reincorporated back into the project as aggregate base. The completed project includes two roundabouts, bicycle lanes, on-street parking, streetscape elements and traffic signal modernization.

    Major Items of Work:

    • Pavement Removal  
    • Storm Sewer     
    • Sanitary Sewer    
    • Water Main      
    • CIPP Sewer Lining    
    • Subbase       
    • Aggregate Base       
    • Concrete Curb/Gutter
    • Concrete Sidewalk 
    • Asphalt Paving        
    156,000 square yards
    10,900 feet
    16,052 feet
    13,711 feet
    7,030 feet
    43,401 cubic yards
    75,000 square yards
    29,400 feet
    168,600 square feet
    30,000 tons

    National Partnership for Highway Quality
    Award Winner

  • W.K. KELLOGG AIRPORT – RUNWAY 5R/23L
  • Location:  Battle Creek, Michigan
    Owner:  City of Battle Creek
    Contract Amount:  $6,625,015.00
    Completion: 2011

    Project Description: Construction of a new parallel runway at W.K. Kellogg Airport. The project involved approximately 285,000 cubic yards of total earthwork. 30,000 cubic yards of muck excavation and over 50,000 cubic yards of fill material imported from off site. New airfield lighting and a new electrical vault building were also constructed as part of the project.

    Major Items of Work:

    • Muck Excavation 
    • Imported Fill 
    • Subbase 
    • Aggregate Base
    • Restoration
    • 12-42” Storm Sewer 
    • Underdrain
    • Asphalt Paving  
    32,000 cubic yards
    55,000 cubic yards
    63,600 cubic yards
    82,500 square yards
    74 acres
    8,250 feet
    21,000 feet
    15,840 tons

  • KALAMAZOO RIVER INVERTED SIPHON REPLACEMENT
  • Location:  Battle Creek, Michigan
    Owner:  City of Battle Creek
    Contract Amount:  $1,533,617.00
    Completion: In Progress, Complete Spring 2012

    Project Description: Construction of a new twin pipe inverted sanitary sewer siphon with new cast in place concrete diversion chamber and outlet structure. The river crossing work was accomplished inside a cofferdam first installed on the north side of the river and then later on the south side.

    Major Items of Work:

    • 24” and 30” DI Pipe         
    • Concrete Encasement
    • 42” CIPP Re-line of Existing
    840 feet
    380 feet
    420 feet

  • DOWNTOWN TRANSFORMATION STREETSCAPE

    Location:  Battle Creek, Michigan
    Owner:  City of Battle Creek
    Contract Amount:  $7,795,243.00
    Completion: In Progress, Complete Fall 2012

    Project Description: Complete reconstruction of Michigan Avenue through the downtown Battle Creek business district. This project is being constructed in 3 phases to minimize the impact of construction on the downtown business district. The scope of the project included replacement of the aging water main and storm sewer infrastructure prior to reconstruction of the roadway. The project also includes numerous streetscape elements such as a fire pit, water fountain and a 40 foot long glass and metal sculpture.

    Major Items of Work:

    • Storm Sewer
    • Water Main
    • Concrete Curb/Gutter
    • Concrete Paving
    • Concrete Sidewalk
    • Decorative Concrete
    • Brick Paving
    • Asphalt Paving
    • Precast  Concrete Benches
    • Street Lighting System
    2,500 feet
    3,700 feet
    7,890 feet
    5,585 square feet
    50,000 square feet
    5,895 square feet
    96,000 square feet
    3,725 tons
    70 each



 

 

 

 

 

 

 

 

 

 

 

 

 

 


 

 

 

 

 

 


 

 

 

 


 

 

 

 

 

 

 

 








 

 

 



Hoffman Bros., Inc.
8574 Verona Road Battle Creek, MI 49014
Phone: 269.965.1207
Fax: 269.965.6701
Email:
generalinfo@hoffmanbrosinc.com

Proud member of Equal
Opportunity
Employer
MDOT Prime Contractor of the Year for DBE Cooperation and Utilization NATIONAL PARTNERSHIP
FOR HIGHWAY QUALITY
AWARD WINNER

Copyright © Hoffman Bros., Inc. 2011